Introduction:
Yarm has a long history of flooding, dating back as early as 1771, when Yarm High Street flooded to a depth of 6 metres.
In 1993, the original Yarm flood alleviation scheme was completed. This scheme involved the construction of flood walls and flood gates to protect Yarm from the River Tees. Unfortunately, in 1995, these new flood defences were overtopped, and Yarm suffered flooding from the River Tees (see photo below). Additional works which built on the previous scheme were then undertaken in 2002. These works involved raising the flood walls by 0.5m (to their current height) and the installation of numerous new flood gates.
In total, the Environment Agency maintains 1.3km of flood wall and 32 flood gates in Yarm, with the defences providing critical flood risk reduction to over 500 homes and businesses.
A project to replace the flood gates in Yarm started in 2017, with 30 flood gates being installed by April 2018. Unfortunately, the flood gates that were installed in 2017 are deteriorating and are challenging for our staff to operate. Whilst the existing flood gates can and will continue to be operated in the short term to protect Yarm, our assessments have concluded that new and improved flood gates are required, providing Yarm with a greater level of flood resilience.
Timescales:
We continue to work on the detailed design of the new flood gates and flood wall improvements. Construction is expected to start in January 2024 and complete in autumn 2024.
We want to give as many opportunities as possible for the local community to give us their thoughts and opinions throughout.
We are running a series of community drop-in events in Yarm library, so keep an eye on this page for details.
You can find our newsletters on this web page, as well as the proposal for some further environmental enhancements.
If you would like more information or have a specific question – just get in touch with us via EA-YarmFAS@environment-agency.gov.uk
The Environment Agency is looking to replace the Yarm flood gates because:
Another benefit of the new gates is that we will be able to shut the gates more quickly. This means that we will be able to shut them later reducing the impact on residents. There will still be some instances where we need to close the gates early.
Over the last 18 months we have engaged with all residents and landowners in Yarm who have flood gates on their properties. We have agreed with all landowners whether their flood gate can be removed and blocked up or replaced. In some instances, we have agreed with the landowner to reduce the opening width of the flood gate.
Thank you for everyone’s cooperation as we’ve gone through this process.
For more detailed information, you can find our newsletters on this web page, dates and times for community drop-in events, or contact us at EA-YarmFAS@environment-agency.gov.uk
Timescales:
We continue to work on the detailed design of the new flood gates and flood wall improvements. Construction is expected to start in January 2024 and complete in autumn 2024.
Everyone is welcome to visit Yarm Library (41 High Street, Yarm, TS15 9BH) on Monday 27 March, from 11:00am - 2pm. This is an informal drop-in session where we will be happy to answer any questions about the Scheme. We will be running more drop-in events, so please look out for the timetable on this webpage.
Everyone is welcome to visit Yarm Library (41 High Street, Yarm, TS15 9BH) on Monday 11 September 2023, from 12:00pm - 3pm. This is an informal drop-in session where we will be happy to answer any questions about the Scheme.
Share
Share on Twitter Share on Facebook