Yarm Flood Alleviation Scheme
Overview
Introduction:
Yarm has a long history of flooding, dating back as early as 1771, when Yarm High Street flooded to a depth of 2 metres.
In 1993, the original Yarm flood alleviation scheme was completed. This scheme involved the construction of flood walls and flood gates to protect Yarm from the River Tees. Unfortunately, in 1995, these new flood defences were overtopped, and Yarm suffered flooding from the River Tees (see photo below). Additional works which built on the previous scheme were then undertaken in 2002. These works involved raising the flood walls by 0.5m (to their current height) and the installation of numerous new flood gates.
In total, the Environment Agency maintains 1.3km of flood wall and 32 flood gates in Yarm, with the defences providing critical flood risk reduction to over 500 homes and businesses.
A project to replace the flood gates in Yarm started in 2017, with 30 flood gates being installed by April 2018. Unfortunately, the flood gates that were installed in 2017 are deteriorating and are challenging for our staff to operate. Whilst the existing flood gates can and will continue to be operated in the short term to protect Yarm, our assessments concluded that new and improved flood gates are required, providing Yarm with a greater level of flood resilience.
Works to install the new flood gates and flood wall improvements began in January 2024 and completion is expected in spring 2025.
Why your views matter
We want to give as many opportunities as possible for the local community to give us their thoughts and opinions throughout.
We are running a series of community drop-in events in Yarm library, so keep an eye on this page for details.
You can find our newsletters on this web page, as well as the proposal for some further environmental enhancements.
If you would like more information or have a specific question – just get in touch with us via EA-YarmFAS@environment-agency.gov.uk
What happens next
The Environment Agency is replacing Yarm flood gates because:
- The existing gates are deteriorating faster than expected. They continue to protect Yarm however the gates do need to be replaced.
- We have a new flood gate specification – using this specification to design new gates means that we will have gates that are safer and easier to operate.
- Wide single leaf swinging flood gates can be dangerous to operate in windy conditions or on uneven ground, putting our staff at risk of injury. Consequently, we have made some gates smaller and changed some to sliding gates to make them safer to operate.
Another benefit of the new gates is that we will be able to shut the gates more quickly. This means that we will be able to shut them later reducing the impact on residents. There will still be some instances where we need to close the gates early.
Over the last few years we have engaged with all residents and landowners in Yarm who have flood gates on their properties. We have agreed with all landowners whether their flood gate can be removed and blocked up or replaced. In some instances, we have agreed with the landowner to reduce the opening width of the flood gate.
Thank you for everyone’s cooperation as we’ve gone through this process.
For more detailed information, you can find our newsletters on this web page, dates and times for community drop-in events, or contact us at EA-YarmFAS@environment-agency.gov.uk
Continuation of works – Third phase of the flood gate replacement has commenced.
The new flood gates on the West side of Yarm (Phase two) which provide access onto True Lovers Walk have been installed and tested, with re-instatement and finalisation of the safe working platforms ongoing. The team are now well underway with the third and final phase of the project, which involves the installation of 5 new flood gates and the infilling of one gate opening, all within private gardens.
We have spoken directly with all landowners and occupants who will be impacted by the replacement of this next phase of gates and we will continue to engage with landowners and stakeholders about the ongoing work, including any further testing we need to undertake on installed gates.
We anticipate that the final phase of the project will be completed by the end of July 2025.
Please note that all dates provided are our best estimate at this moment in time, and may change, especially if we experience poor weather and the flood gates need to be operated.
Image showing Gate 20-22 near the Yarm Road Bridge
True Lovers Walk
We fully understand the use and enjoyment that the community gets from the True Lovers Walk and note the impact on the community when this public footpath is out of use.
Due to the need to create a safe working environment, the closure of sections of True Lovers Walk during the works has been required. Where closures have been required, we have done this in a phased manner to reduce impacts to the local community.
The works and associated reinstatement on the West side of Yarm along True Lovers Walk are close to being completed. This work is a critical part of the project and involves the construction of new access steps and platforms which are designed to provide a safe working area for our staff when operating the new flood gates.
We are pleased to advise that the majority of the construction works have been completed, however access for plant is still required along True Lovers Walk to accommodate the remaining works and reinstatement of the path. Access along the western section of True Lovers Walk will continue to be restricted until mid-May 2025.
Image showing new passing places installed on True Lovers Walk – tarmac to be laid.
Whilst we understand that this could be inconvenient to walkers in the short term, this closure is necessary to facilitate access needs and means that we can safely deliver the scheme. We want to reassure residents that we are doing everything possible to re-open the remaining sections of footpath as soon as we can. We apologise for any inconvenience our activities may cause and thank you for your continued patience and cooperation.
As part of the scheme’s drive to deliver environmental enhancement, we had planned to plant some trees and hedging along True Lovers Walk during February and March 2025. Unfortunately aligning this with the ongoing re-instatement hasn’t been possible, so the planting will now be undertaken during the next planting season, in Autumn 2025 – closure of the footpath should not be required to deliver this planting.
Please note that all dates provided are our best estimate at this moment in time, and may change, especially if we experience poor weather and the flood gates need to be operated.
Events
-
Yarm FAS - community drop-in event
From 27 Mar 2023 at 11:00 to 27 Mar 2023 at 14:00Everyone is welcome to visit Yarm Library (41 High Street, Yarm, TS15 9BH) on Monday 27 March, from 11:00am - 2pm. This is an informal drop-in session where we will be happy to answer any questions about the Scheme. We will be running more drop-in events, so please look out for the timetable on this webpage.
-
Yarm FAS - community drop-in event
From 11 Sep 2023 at 12:00 to 11 Sep 2023 at 15:00Everyone is welcome to visit Yarm Library (41 High Street, Yarm, TS15 9BH) on Monday 11 September 2023, from 12:00pm - 3pm. This is an informal drop-in session where we will be happy to answer any questions about the Scheme.
Audiences
- Anyone from any background
Interests
- Flood management
- Specific projects, issues, or activity pages
Share
Share on Twitter Share on Facebook