While we were changing our designs around the A423 to accommodate the proposed bridge replacement we also took the opportunity to review and update some other aspects of our scheme.
The progress is summarised below - please click on each item for more detail.
This approach will benefit private road users and will also ensure that the existing bus routes that use Old Abingdon Road and Kennington Road will not have to be diverted.
In summer 2020 we carried out ground investigation work to complete our design for the temporary road.
Diagram showing location of temporary road
Once the construction period has finished and the temporary road removed, we will plant new trees in Kendall Copse. We will replant with native trees and where we’re unable to plant as many trees as before, we will compensate for this by planting trees in other locations locally. Although we will need to temporarily stop access to Kendall Copse during construction, we plan to provide public access to the newly planted Kendall Copse once we finish. We will also install an interpretation board to explain the history of the scheduled culverts which were part of a medieval causeway under the Old Abingdon Road.
When we designed the Oxford Flood Alleviation Scheme, we looked at moving the excavated material such as earth and gravel by rail. At the time of our previous planning application, the rail sidings were already in use, and we planned instead to move surplus material by road. Since then, local residents asked us to re-look at the rail option.
Changes to the construction date have provided an opportunity to use the rail sidings and we are now actively pursuing the option of moving some excavated material by rail. Our preference is to use rail. However as the construction date is still some time away, we cannot confirm with certainty that the sidings will be available for us to use. We will be submitting a separate planning application, for the movement of the majority of excavated material to the rail sidings, to be transported by rail.
The separate planning application will cover the additional land and changes required if we transport material by rail. This will include a haul road from our compound north of South Hinksey to the Hinksey Rail sidings. The planning permission for the rail element will only be implemented if the planning application for the main scheme is granted.
Building the Oxford Flood Alleviation Scheme will reduce the likelihood of floods in built-up areas. Flooding increases carbon emissions due to direct damage and disruption, as well as the replacement and refurbishment of properties, vehicles and belongings. An Environment Agency research project has been looking at how flood schemes account for both carbon emitted as well as carbon avoided in the future as a result of reduced flood risks to properties. The purpose is to help projects consider the whole-life carbon balance of options alongside the need to reduce carbon emissions of our construction and maintenance as much as possible. This work is in its early stages but shows that by reducing flooding, the Oxford scheme will prevent the production of far more carbon emissions in the long term than are generated through its construction and maintenance.
We have also been reviewing how we can reduce our carbon footprint in constructing and maintaining the scheme as much as possible. This includes looking at the materials we are using and the way that we build the scheme, as well as the way we will look after it in the future.
The design of the scheme to create a stream with wetland habitat, with limited need for maintenance, fits with a lower carbon approach. Sustainable features include:
Following the recent design changes to the scheme we have recalculated our carbon emissions. Our carbon forecast for the future operation and maintenance of the scheme after construction has reduced since our last planning application. These updated figures are presented in our new planning application.
Most of our carbon emissions will be from machinery and vehicles needed to move material and from producing the concrete and steel we will use. We continue to explore ways to reduce the carbon generated through construction and maintenance, including how we might use current and future technology.
The Environment Agency has formed a new collaboration with the environmental charity Earth Trust.
We are working with Earth Trust on our plan for the long term environmental and wellbeing benefits of the scheme. This partnership will help us make the most of this unique opportunity – ensuring the new landscape and habitats continue to enhance the local area for the lifetime of the scheme.
Once we have all the necessary approvals and are nearing construction of the scheme, we will appoint an environmental partner who will be responsible for looking after the wildlife and landscapes of the scheme area. They will continue our work to bring additional environmental enhancements, involve local people and interested groups and establish educational outreach and opportunities for scientific research. In this way the Environmental Vision will deliver a long term green legacy to the area.
One of our main environmental objectives is for the scheme to deliver a net gain in biodiversity. ‘Biodiversity net gain’ means leaving more good quality natural habitats and ecological features after a development is built than beforehand. We are ensuring the scheme’s features such as the new stream, ponds, wetland and floodplain meadow will leave the area with a greater variety of wildlife than before. This includes ensuring any unavoidable habitat loss while we build the scheme is more than compensated for by new habitats.
Since our previous planning application was submitted, Natural England has updated the way that biodiversity net gain should be calculated. Since this is such a rapidly evolving and emerging field of work, we are continuing to liaise very closely with the ecologists at Oxfordshire County Council, Oxford City Council and the Vale of White Horse, as well as with Natural England, the local Wildlife Trust and other key environmental stakeholders to ensure that we are delivering a net gain in biodiversity. We have provided the most up to date information on our biodiversity improvements in our new planning application.
Share
Share on Twitter Share on Facebook