Sanway-Byfleet Flood Alleviation Scheme

Closes 29 May 2026

Opened 12 May 2022

Overview

Overview

This web page has been set up to share information about the Sanway-Byfleet Flood Alleviation Scheme. 

The scheme is being developed by the Environment Agency in partnership with Woking Borough Council, Surrey County Council, Surrey Wildlife Trust, Byfleet Flood Forum, National Highways, Royal Horticultural Society, Thames Water, and the local community.

The scheme reduces flooding to properties in the Sanway area with new flood walls and embankments, storage areas for displaced flood water and environmental and community enhancements.

If you want to be kept up to date with our progress or have any questions about the scheme, contact us at thm.schemes@environment-agency.gov.uk

Scheme Location

The map below shows the area covered by the scheme. 

Sanway-Byfleet Flood Alleviation Scheme location plan

Background

Byfleet has experienced several notable floods in 1968, 2000 and 2003. Recently, in 2013/14 prolonged heavy rainfall resulted in flooding from the River Wey and a total of 74 properties were flooded.

Following the winter 2013/14 flood a high-level meeting was held between the Environment Agency and Surrey County Council.

The Environment Agency agreed to review options to reduce flood risk at several locations in the Byfleet and Weybridge area and identified an economically viable scheme for the Sanway area in Byfleet.

The scheme now aims to better protect up to 236 properties in the Sanway area of Byfleet from river flooding, taking climate change into account.

Sanway-Byfleet area, 1968

Byfleet has a long history of flooding, with a large flood in September 1968 causing significant damage to properties along the River Wey. It was one of the largest floods seen in this area and was estimated as being a 1 in 200 chance of flooding. 

The below image shows a snapshot of the flood in the Sanway-Byfleet area in 1968.

Modelled flood risk May 2022

The maps below show the current likelihood of flooding in the area without a scheme and future flood risk with alleviation measures.

Flood risk without alleviation measures

Flood risk with alleviation measures

Our surveys

We have carried out a range of surveys and investigations to improve our understand of the area and inform our designs. These are summarised in the table below.

Survey What we have learnt
Ground investigation Obtained geotechnical and geological data to inform flood scheme designs, assess contaminated land risk and assess the suitability of excavated material for re-use in the flood walls and embankments.
Groundwater level monitoring Provide long-term monitoring of groundwater levels across the site to inform design of the flood walls and embankments.
Ecological surveys Identified constraints including bat roosts, breeding birds, reptiles, badgers, great crested newts, and invasive non-native plantts. Informed calculations to assess biodiversity net gain.
Tree surveys Gathered basic data and records of the condition of the trees by visual inspection in accordance with British Standards.
Archaeological surveys Archaeological trial trenching ring 2024 to assess the potential impact of proposed works on any archaeological heritage on the site.
Topographic surveys Gathered ground level data to inform design of flood walls and embankments, compensatory floodplain stoorage areas and lanscape proposals.

Our proposed flood scheme

Flood walls and embankments

To reduce flooding from the River Wey, we propose to install a combination of flood walls and flood embankments. These protect homes by acting as barriers to flood water.

The flood wall and embankment will range in height depending on whether the land is low lying. The western end of the scheme ties into the M25 embankment next to Broad Ditch and runs east in Common Meadows along the rear boundary of properties in the Fullerton Road and Sanway Road area. It then runs northwards to protect properties in Summer Close before ending on higher ground.

The wall and embankment will not increase flood risk to other areas because the scheme will also involve the creation of new areas of floodplain storage”, which will hold the floodwater that is displaced by the flood wall and embankment.

Our current scheme proposals include:

  • Sheet pile flood wall from the M25 to the southern end of Sanway Road.
  • Earth flood embankment between the southern end of Sanway Road and Summer Close.
  • Three compensatory floodplain storage areas.
  • A normally dry overflow channel west of the M25 between the Broad Ditch and the River Wey.
  • Improvements to surface water drainage pipes that run underneath the flood embankment, to ensure flood water cannot bypass them.

The plan below shows the proposed alignment of the flood wall and embankment and the areas where we require compensatory floodplain storage. You can also download a PDF of the plan. 

Sanway-Byfleet Flood Alleviation Scheme proposal

Environmental improvements

While the aim of the scheme is to reduce flooding, we also have an opportunity to deliver some wider benefits to the community and the natural environment in the area.

Environmental improvements may include:

  • Increased biodiversity of habitats within Common Meadows and Manor Farm.
  • Enhancement of existing grassland areas to more distinctive grassland habitats (i.e. lowland meadow).
  • Creation of wetland features and ditches linked to the River Wey and increased marginal planting along the riverbanks.
  • Providing a net increase in length of hedgerows within Manor Farm (currently under discussion with Surrey Wildlife Trust).
  • Creation of pockets of wet woodland (woods that occur on ground that is often or seasonally wet).
  • Enhanced provision and connectivity of footpaths and bridleways within Common Meadows and to the wider network both west of the M25 and northeast into Manor Farm.
  • Improvements to M25 underpass - improve daytime lighting, repainting and removal of fencing.

We have identified a range of measures necessary to protect the environment and local communities before and during construction and once the scheme is in place. For example, minimising noise, checking air quality and traffic flow impacts. We are also going to provide habitat improvements and aim to achieve a 20% biodiversity net gain in each of the 3 components: terrestrial habitats, hedgerows, and rivers.

Example photo of riverbank enhancement on the River Wey

Before construction begins, we must make sure that all approvals, such as planning permission, are in place. Provided the scheme is fully approved and funded, the earliest construction could be completed is winter 2025.

What will the scheme look like?

The diagrams below shows the current landscape proposals for the Sanway-Byfleet area.

Sanway-Byfleet Flood Alleviation Scheme landscape plan: October 2023

Proposed landscaping plan for Common Meadows: October 2023

Aerial view of Common Meadows

Artist's impression view of Common Meadows towards Fullterton Road

Artist's impression of entrance to embankment from Muddy Lane

Artist's impression of the flood embankment north of access from Fullerton Road

Example of recently constructed flood embankment at Marlow. Pictures A and B show an embankment, and picture C shows the access path over the embankment.

Floodplain storage area

Artist's impression of Manor Farm floodplain storage area

A floodplain storage area is where the ground levels will be lowered to provide space for floodwater that is displaced by the construction of the flood wall and embankment.

The land will be reseeded to provide enhanced grassland increasing biodiversity.

Construction

Embankment design

The sketch above shows how the embankment will be constructed. This includes the flood wall, soil and piling rig. Water held back by the flood embankment will slowly seep through the soil coming out on the dry side of the embankment. To stop this, we will install an impermeable 'cut off' through the embankment into the ground below. Our preferred method to create the 'cut off' will be to mix in the ground the existing soil with cement to create an impermeable wall.

The photos show the typical equipment used for soil mixing. Similar equipment will be used for the flood alleviation measures in this project.

The working hours for construction of the scheme are 08:00 to 18:00 Monday to Friday. We will be working across all areas of the construction site. While there may be times when construction is not visible, we will still be working on that area.

We will do everything we can to reduce disruption like using the most up to date technology, looking at options to reduce vehicle movements ad putting up site boards and fencing to reduce visual and noise effects.

Scheme costs and benefits

The benefits of the scheme include:

  • Better protection from flooding of people and properties in Sanway.
  • Improved recreational access to Common Meadows and Manor Farm.
  • Biodiversity and habitat improvements.

Based on current information, we anticipate the scheme will cost in the region of £18 million to £20 million. The cost of the scheme includes:

  • Detailed design and planning application (including further surveys).
  • Construction of the scheme.
  • Maintenance of the scheme over the next 100 years.
  • Contingency allowance for increases in costs as the scheme develops.

The Environment Agency, Surrey County Council, the Regional Flood and Coastal Committee and the national government are all making considerable contributions to the scheme. 

Target dates

The following dates are subject to stakeholder agreement, planning permission and funding approvals.

Public engagement

We have been developing the scheme over the last few years and are now in the detailed design stage where we have identified our preferred option.

We ran a public engagement event in autumn 2023, with previous events in May 2022, March 2021 and February 2019.

We have used feedback from these events to inform the development of the flood alleviation scheme.

We have also issued newsletters to keep the local community informed of scheme progress.

How to take part

You can contact us at any time by:

Email at THM.schemes@environment-agency.gov.uk

Telephone at 03708 506 506

Post at Sanway-Byfleet FAS, Kings Meadow House, Kings Meadow Road, Reading, RG1 8DQ

Privacy Policy

What this policy covers

We, Environment Agency, take our privacy obligations seriously and we’ve created this privacy policy to explain how we treat your personal information collected on this website. Personal information is information we hold which is identifiable as being about you.

Our collection, use and disclosure of your personal information is regulated by the European Union’s General Data Protection Regulation (‘GDPR’) and the Data Protection Act 2018.

What personal information we collect

Profile Information

We collect information from you when you register to use this site. This includes your email address and additional demographic information as provided by you on the registration form.

Please note that you are able to browse any publicly accessible sections of this website completely anonymously without signing up.

Engagement Information

The content you create as part of your interactions with this website. These can include responses to surveys, comments on discussion forums, or any of the other engagement opportunities available here.

Usage Information

We collect information about your usage of the site, such as pages visited, documents downloaded, etc.

How we use the information we collect

We collect this information in order to:

  • analyse and interpret it to help meet our objectives and obligations;
  • communicate information to you about our engagement opportunities, events and other initiatives; and
  • respond to enquiries and otherwise engage with stakeholders.

External links

Our website may contain links to other websites. Those links are provided for convenience and may not remain current or be maintained. We are not responsible for the privacy practices of linked websites and we suggest you review the privacy policies of those websites before using them.

Where this website contains links to other sites and resources provided by third parties, these links are provided for your information only. Such links should not be interpreted as approval by us of those linked websites or information you may obtain from them.

We have no control over the contents of those sites or resources.

Security

While no online service is completely secure, we work very hard to protect information about you against unauthorized access, use, alteration, or destruction, and take all reasonable measures to do so.

Requesting access or correcting your personal information

Subject to applicable local laws and regulations, you may have some or all of the following rights with respect to your personal data:

  • to access your personal data and to rectify any inaccuracies within that personal data;
  • to request for the erasure of your personal data residing with us;
  • to request your personal data in portable, machine-readable format; and
  • to withdraw your consent to our processing of your personal data.

If you wish to contact us to with a request relating to personal information we hold about you, please contact us using the contact details set out below including your name and contact details. We may need to verify your identity before providing you with your personal information.

In some cases, we may be unable to provide you with access to all your personal information and where this occurs, we will explain why. We will deal with all requests for access to personal information within a reasonable timeframe.

Contact us

For further information about our privacy policy and related information practices, or to access or correct your personal information, or make a complaint, please contact us on thm.schemes@environment-agency.gov.uk

 

If you want to stay in touch with scheme progress please add your contact details

Audiences

  • Members of the public

Interests

  • Flood management
  • Specific projects, issues, or activity pages