The River Roding Project information page
Overview
Updated 16 October 2024
This page provides a summary of the latest progress and an overview of our project which aims to reduce flooding to homes, businesses and infrastructure in the Woodford and Ilford areas. It also sets out who you can contact for further information, and how to request to be added to our mailing list.
There is a set of Frequently Asked Questions at the bottom of the page, which will be updated regularly throughout the construction phase.
This page will be reviewed every 3 months and updated as necessary.
Latest project progress
Since our last update in July 2024, the two main areas of focus on the project have been:
- Continuation of the main works to construct a Flood Storage Area on the River Roding just north of the M25 at Shonks Mill Bridge.
- Refurbishment of an existing flood embankment in Woodford to make sure it can withstand the estimated impact of climate change.
Figure 1 below shows the location of these works and there is an update on these 2 main elements of the project below.
Above: Figure 1 - map showing the location of the River Roding project works
Woodford embankment work
At the end of September 2024, BAM Nuttall started work on a repair to an embankment in Woodford, behind Broadmead Baptist Church. These works are an important part of the overall project to achieve the flood risk benefits for communities in Woodford and Ilford. They have undertaken bat surveys and vegetation clearance, and will now be setting up the site compound, undertaking tree work, carrying out the embankment repairs, then finish with landscaping works. This is predicted to be complete by the end of October 2024. We produced a one-sided briefing note specifically relating to these works, which is linked at the bottom of this page. This was provided to the Church and BAM Nuttall contractors on site had copies to provide to any passers by. Figure 2 below shows the location and approximate extent of these works.
Above: Figure 2 - location of Woodford embankment works adjacent to Broadmead Baptist Church, Woodford
Flood Storage Area at Shonks Mill
Since we entered the into the construction contract with BAM Nuttall in March 2024, work has focused on the following key activities:
- The first 3 months of the programme focused on vegetation clearance, establishment of access points to the site and set-up of the site compound.
- Since June 2024 when the permanent construction works started, BAM Nuttall have been working on the following:
- Piling and excavation of the cofferdam to enable the river control structure to be built. A cofferdam is a watertight enclosure, created using sheet piling to establish a dry working area (see figure 3 below).
- Excavation of the river diversion channel, where the River Roding will be diverted once the control structure is operational (see figure 4 below).
- Installation of a temporary river crossing to enable access to the eastern side of the site where material (clay) is being excavated to build the earth embankment (see figure 5 below).
- Diversion of the public right of way across the site to its new permanent route.
- Construction of an artificial badger set.
There is more detail on each of these activities in the diagram and table below, as well as some recent photographs showing progress of work on site:
Above: Figure 3 - inside the cofferdam, which is being excavated to create a dry working area to build the control structure
Above: Figure 4 - excavation work on the River Roding diversion channel
Above: Figure 5 - temporary crossing over the River Roding to the site of the material (clay) excavation
Above: Figure 6 - the site pictured from above, showing the river diversion works at the top and the cofferdam on the right
Below, figure 7 shows the site from above and the location of the individual activities being undertaken by BAM Nuttall. Additional detail of each activity is in the table below the image.
Image reference |
Description of work being delivered |
|
This was one of the early activities which was completed to provide welfare facilities, office space and car parking for the site. |
|
This access point was established early in the programme of works, to enable vehicles to safely enter the site. Road closures were in place whilst it was implemented, but now it is the main access point, and the road is open as usual. Signage has been installed so that passers-by and those entering the site understand who is working there and what the project is about. |
|
An artificial badger set is being installed adjacent to the woodland, as some of the current badger sets need to be closed to enable the earth embankment to be constructed. This work is underway now and the set should be available for badgers to find it by the middle of October. |
|
The Public Right of Way (footpath) which crosses the site needed to be diverted as the original route will be inaccessible once the embankment is constructed. This new route is now in place on the ground and remains accessible to anyone who wants to use it (with a gate which will be opened when required). |
|
The work to finalise the cofferdam is still ongoing, and once complete will create a dry working area to allow construction of the control structure. The control structure is an important element of the project which controls the amount of flow which the river passes downstream to provide flood risk benefit to communities. |
|
The River Roding is being diverted through a new wetland as part of the project, and the work to create the new channel is in progress as can be seen in figures 4 and 6. This will not be connected at the upstream and downstream ends until the control structure is complete. |
|
The project is utilising a field to the eastern side of the site to excavate material (clay), which will be used to construct the earth embankment. For this to be accessible to the contractors on site, a temporary bridge was required over the existing River Roding channel. This is now in place, allowing vehicle access to the other side of the river. It will be removed once the project is complete. |
|
The blue line on the image shows the existing, overly straightened, course of the River Roding. As explained above, part of the project includes diverting this river through a new wetland area, before it passes through the control structure. |
What's next?
The diagram below shows the high-level activities which will take place within the next 6 months of the flood storage area construction programme:
We will update this diagram regularly as the project progresses. We expect to complete the construction in early 2027.
Why are we doing these works?
There has been an increased frequency of flood events over the past 20 years. The most serious flood in recent decades occurred in October/November 2000. Over 400 homes in Woodford were flooded, there was widespread disruption to local infrastructure and major roads (including Charlie Browns roundabout) were closed for over a week. Climate change data shows that the frequency and intensity of such events will increase over the coming years, so it is important we reduce the impact of flooding on the local area.
As well as the economic damage that occurs after a flood event, flooding also has an impact on peoples' wellbeing. Flooding often causes financial stress, disruptions to daily life and can impact peoples' mental health (see figure 8 below).
Above: Figure 8 - some of the impacts flooding can have on people's wellbeing
The photos below show flood events which have affected the communities in Woodford and Ilford.
Above: Figure 9 - aerial photograph of the Roding flooding in December 2019, taken by a local resident
Above: Figure 10 - Photo taken during the floods in 2000.
Project background
The River Roding Project will reduce flooding to residential properties, commercial properties and infrastructure in the Woodford and Ilford areas.
The project includes building a flood storage area on the River Roding, upstream of the M25, at Shonks Mill Bridge. The flood storage area will allow the river to flow naturally most of the time, however in times of high flows, water will build up and be stored behind the earth embankment creating a temporary reservoir, reducing the risk of flooding downstream. This will then drain naturally back into the river as flows reduce.
The project also includes refurbishing a flood embankment downstream in Woodford to withstand the estimated impacts of climate change.
The before and after diagrams in figure 11 below show how a flood storage area works. In times of high flows, flood water is held behind the earth embankment while a controlled flow will be able to pass through the structure, reducing the flow, and extent of flooding downstream.
Figure 12 below shows an artists impression of how the embankment will look on the River Roding at Shonks Mill once it is complete.
Above: Figure 11 - diagram showing how flood risk is reduced to downstream communities by a flood embankment and control structure
Above: Figure 12 - artists impression of the completed flood storage area embankment above Shonks Mill Road
If you would like to ask the project team any questions, then please contact us using the email address on the right-hand side of this page. If you would like to be added to our mailing list so that you are kept updated about the project, and notified when this website is updated then please send us an email and we will add you to our list.
Please note our proposals will reduce the risk of flooding and climate change impact but will not eliminate the risk altogether.
Are you prepared for flooding?
- Sign up to flood warnings and give yourself time to protect yourselves and your valuables. Visit www.gov.uk/sign-up-for-flood-warnings or call Floodline on 0345 988 1188 to check your areas is covered and sign up to receive real-time alerts.
- Know what to do if it floods with a personal flood plan. Download a template: www.gov.uk/government/publications/personal-flood-plan
-
Help your community build flood resilience by creating a community flood plan. Download a template: www.gov.uk/government/publications/community-flood-plan-template
Audiences
- Recreational and commercial river users
- Fishing clubs and representative associations
- Members of the public with an interest in the river, the species and conservation
- Businesses
- Charities
- Statutory organisations
- NGOs
- Members of the public
- Elected representatives, including MPs
- Local councils
- Local authorities
- District and parish councils
- Environmental bodies
- Land owners
- Water companies
- Members of the public
- Recreational and commercial river users
- Community groups
- Flood action groups
- Members of the public
- Community groups
- Lead Local Flood Authorities
- Local Risk Management Authorities
- Members of the public
- Town and parish councils
Interests
- Flood management
- Water quality
- Habitats and wildlife
- Specific projects, issues, or activity pages
Share
Share on Twitter Share on Facebook