Lydd Ranges Sea Defences Scheme - Upcoming works

Closes 23 Jul 2025

Opened 21 Jul 2021

Overview

September and October 2021 Update

Construction of the scheme will take place over 3 years, with works being undertaken during the spring, summer and autumn months each year. The on-site works commenced in July and works undertaken to date include:

  • Preparation of the site compound area.
  • Commencement of the installation of timber groynes on the beach: the first stage of groyne construction involves driving “piles” (vertical posts that provide support for the timber planks) into the beach, using a “movax” vibration piling machine. An impact hammer (a large hammer that creates a different, ‘banging’ sound) is only required to drive the pile to the final depth as the soil becomes more resistant during the pile driving operation. The impact hammer sound is intermittent and not continuous. This equipment was used during the emergency works at Lydd (50m east of the MOD lookout) in 2020. Piles for 7 of the 34 groynes have now been installed.
  • Preparations for the works to improve the access road along the Green Wall embankment have commenced, which to date have involved temporarily removing some of the rock to provide access to the seaward edge of the road.
  • Commencement of the interim beach nourishment operation in mid-August: this interim beach nourishment operation involves the importation and placement of approximately 46,000m3 of shingle to the 600m of beach to the east of the MOD lookout. A dredger collects the material from a licenced borrow area located 30 nautical miles off the coast of Eastbourne. The material is then loaded onto flattop barges, which bring it to the beach at high tide. Once delivered to the beach, bulldozers and wheel loaders distribute and profile the material. This operation on the beach takes place 24 hours a day 7 days per week, so you may have noticed some recent coming and going at the site compound area at all hours. The plant is fitted with modified reverse alarms to reduce noise.

Groynes being constructed at nearby Hythe Ranges

Works proposed for September and October 2021 include:

  • Timber groyne construction throughout September and October:
    • Timber for the groynes will continue to be delivered to the site compound at Jury’s Gap.
    • Timber preparation: Where possible, the timber will be prepared off-site to minimise the noise and disruption to those local to the Jury’s Gap compound. Where timber preparation is required at the Jury’s Gap compound, this will be during one high tide 6-hour shift each weekday (during the day, not at night). The work involving chainsaws will not be continuous during the hours of high-tide as there will also be other works occurring. Acoustic fencing will be installed to reduce the noise and we will also have use of another site within the MOD ranges to try and minimise the impact.
  • Groyne construction: works continuing to take place on the beach, mostly during low-tide, each weekday during daylight hours. In September and October we are working at groynes further down the beach away from properties (approx. 500 m east of the MOD lookout) and machinery and equipment for the groyne construction will be stored local to the working area on the beach, where possible. Deliveries of plant and equipment to the compound at Jury’s Gap and South Brooks (within the MOD ranges) will continue to use the sea wall to access the ranges to the east of the cottages. On average, less than one delivery per day is expected during September and October.
  • Preparing for the construction of the access road from Jury’s Gap lookout to Wicks will commence in September. To do this we will need to break out the existing road, starting mid-September and this is expected to take about 4 weeks, but these works are at least 250m from properties.
  • Beach recharge works are expected to be completed mid-September. The beach recharge works will be working over a 600m stretch of beach roughly from the MOD lookout working east – so working away from properties.

To go back to the homepage please click here. 

If you have any queries about the scheme or would like to sign up for our email circulation list please contact us via our project inbox at lyddranges@environment-agency.gov.uk.

Audiences

  • Recreational and commercial river users
  • Fishing clubs and representative associations
  • Members of the public with an interest in the river, the species and conservation
  • Businesses
  • Charities
  • Statutory organisations
  • NGOs
  • Members of the public
  • Elected representatives, including MPs
  • Local councils
  • Academics
  • All water abstractors
  • Environment Agency customers
  • Net fishing license holders
  • Angling trade contacts
  • National based fishery, conservation and landowner organisations
  • Government family organisations
  • IDBs
  • Local authorities
  • District and parish councils
  • Environmental bodies
  • Land owners
  • Farming associations
  • Drainage associations
  • RFCCs
  • Elected representatives, including MPs
  • Water companies
  • Members of the public
  • Recreational and commercial river users
  • Community groups
  • Flood action groups
  • UK Border Force
  • Members of the public
  • Community groups
  • Non-governmental organisations with an interest in environmental issues
  • Environment Agency colleagues
  • Lead Local Flood Authorities
  • Local Risk Management Authorities
  • Flood Resilience Forums
  • Members of the public
  • Town and parish councils
  • Engagement specialists/operational staff in Natural Resources Wales, local authorities and other risk management authorities

Interests

  • Business and industry
  • Flood management
  • Coastal management
  • Fishing and boating
  • Water resources
  • Water quality
  • Drought
  • Habitats and wildlife