Updated on 20 May 2022
Carrara Wharf is on the northern shore of the River Thames in Hammersmith and Fulham. Within this area, is a draw dock which forms part of the River Thames and protects the local community from flooding.
The eastern and northern walls of the draw dock are now at the end of their serviceable life and need to be repaired.
The construction phase of this project is currently planned for mid-2023. The works are expected to take approximately 50 weeks. This includes the site compound set-up, the construction of the piling mat in the draw dock, the piling, and the demobilisation from site.
The work is part of the Thames Estuary Asset Management 2100 (TEAM2100) Programme which is delivering the first 10 years of a programme which aims to ensure tidal walls, embankments, and barriers along the Thames Estuary continue to protect 1.4 million people and £321 billion of property from tidal flooding.
Investigations in June 2020 highlighted that the flood defence requires urgent work so it can continue to function as an active flood defence and better protect approximately 300 people from flooding.
The work will repair and stabilise the eastern and northern flood defences to help better protect the community. TEAM2100’s role is also to consider the longer-term management of these flood defences into the future, making managing the defences more cost-effective for the flood defence owners.
There is an opportunity as part of the Carrara Wharf project to enhance the draw dock. This could take the form of artificial rock pools attached to the side of the walls to encourage species diversity, the creation of vegetated area to encourage wildlife, and further environmental improvements. We are working with Thames21, who work with communities to improve our rivers, canals, ponds and lakes for people and wildlife, to discuss opportunities as the project progresses.
We will prepare and submit consents applications for the proposed works as required, including:
This is an online information page which will be regularly updated with project specific information, there is no formal consultation activity requirements for this page.