Standard Rules Consultation no. 24: introduction of two new standard permits for: (a) recycling scrap metal and (b) processing end-of-life vehicles
Results updated 17 Feb 2022
In June 2021, we ran our consultation for two new standard rules permits. We wanted to hear your views on the following new standard rules permits which included Fire Prevention Plans (FPP):
- a small metal recycling facility (less than 5,000 tonnes) with associated fire prevention plan, and
- a small end-of-life vehicle depollution and dismantling facility (less than 750 tonnes) with associated fire prevention plan.
How we ran the consultation
We ran a formal consultation on our Citizen Space online consultation tool and GOV.UK from 28 June 2021 until 20 September 2021.
In total we asked 42 questions. Questions (Q) relating to the small metal recycling facility (less than 5,000 tonnes) were set out in Q1 to Q18 of the consultation. Questions relating to the small end-of-life vehicle depollution and dismantling facility (less than 750 tonnes) were set out in Q19 to Q42.
We received all 6 responses to our consultation online from:
- 2 responses from trade associations
- 1 response from an individual
- 1 response from a business
- 2 responses from operators of waste management facilities
Summary of key findings and actions we will take
Your views were supportive of the two proposed new permits and associated FPPs.
We are now reviewing these draft permits with reference to the comments received and we will produce final versions for publication on GOV.UK.
Our aim is to publish these two permits in spring 2022.
Should you want to follow up on your responses or have questions relating to this consultation response then please contact us at wastetreatment@environment-agency.gov.uk including “Standard Rules Consultation no. 24” in the subject of your email.
Next Steps
Please see our consultation response document for a full summary of your responses on GOV.UK.
Thank you for participating in our consultation.
Links:
Overview
We are the Environment Agency. We protect and improve the environment.
The Environmental Permitting (England and Wales) Regulations 2016 allow us to make standard rules permits that reduce the administrative burden on businesses while maintaining environmental standards.
This consultation is about 2 new standard rules permits that will allow operators to:
- store and treat up to 5,000 tonnes of ferrous and non-ferrous metals each year
- operate a vehicle storage, depollution and dismantling facility for up to 10 end-of-life vehicles per week
The new standard rules permits are for small scale operators. They include a fire prevention plan to make sure operators comply with our fire prevention plan guidance.
In 2018, the Department for Environment, Food and Rural Affairs (Defra) and the Welsh Government, carried out a public consultation ‘Reducing crime at sites handling waste, and introducing fixed penalties for waste duty of care’. They proposed making substantial changes to the waste exemptions regime including changes to exemptions T9 (recovering scrap metal) and U16 (using depolluted end-of-life vehicles for parts).
Although the outcome of the consultation has not yet been published, the aim of introducing these new standard rules is to help operators, if they are required to transition from these exemptions into environmental permitting.
The new standard rules permits are supported by generic risk assessments. We have produced the generic risk assessments to make sure that risks to the environment and human health are kept to a minimum.
We want your views on whether the proposed 2 new standard rules permits, fire prevention plans and generic risk assessments are appropriate to manage the risks of the permitted activities.
What a standard rules permit is
Standard rules permits contain one condition which refers to a fixed set of standard rules that an operator must comply with. The rules define the activities that an operator can carry out and specify necessary restrictions on those activities, such as waste storage quantities and emission limits. Standard rules are published on GOV.UK following public consultation.
Further information on standard rules permits can be found in the Fact Bank below.
The consultation document can be seen below and can also be found here. To access the new permits and generic risk assessments, please scroll down to 'related documents' section.
More Information
The fire prevention plan is included with each rule set
We have produced a fire prevention plan (FPP) for each rules set we are consulting on. This is set out in schedule 3 of the permit. The requirements specified in schedule 3 address the risks posed by the permitted activities set out in condition 2.1 and the waste types listed in schedule 1 of the permit. The fire prevention plan satisfies the 3 objectives set out in our FPP guidance, which are to:
• minimise the likelihood of a fire
• aim for a fire to be extinguished within 4 hours
• minimise the spread of fire within the site and to neighbouring sites
The standard rules require the activities to be carried out in accordance with the fire prevention plan. Failing to comply with the requirements of the fire prevention plan will breach the permit conditions.
If an operator cannot fully comply with the fire prevention plan or the activities, or waste types change, they must vary their permit. They will need to submit a site-specific fire prevention plan as part of their application to vary their permit.
Generic risk assessments for these activities
We have produced generic risk assessments for these activities. They list the potential risks and how to manage them. We identify possible pathways from the risks to the receptors (people, animals, property and anything that could be affected by the hazard).
The risk assessments are split into 3 sections:
- data and information – this section is made up of receptor, source, harm and pathway information that is relevant to the activity
- judgement – we have done the risk assessment to work out the likelihood of the receptors being in danger from the hazard, the consequences of the hazard happening and the overall size of the risk
- action – risks will be controlled by setting standard rules. For example, to manage noise and vibration, operators must comply with a relevant noise and vibration management plan
We will control residual risks by doing compliance assessment, such as site inspections, to ensure that the operators comply with the rules.
A set of standard rules may contain a rule which requires an operator not to carry out an activity within a certain distance of specified nature conservation sites. Habitats and species are sensitive to toxic contamination, nutrient enrichment, habitat loss, silt, smothering, disturbance and predators.
We use specified distances to identify which activities could affect sites and species. Activities that do comply can be eligible for a standard rules permit. We do not consult nature conservation bodies on individual applications for standard rules permits.
Proposed charges
These charges apply to both rules sets. They try to cover Environment Agency costs.
Permit application: £2,641
Minor variation: £792
Transfer application: £2,529
Surrender application: £1,585
Annual subsistence: £971
Summary of the proposed rules we are consulting on
These new standard rules sets do not replace any other standard rules currently in place.
Small metal recycling facility (less than 5,000 tonnes) with associated fire prevention plan (SR 2021 No.11) will allow the operator to:
- operate a metal recycling facility that accepts no more than 5,000 tonnes of specified ferrous and non-ferrous wastes per year – the combined storage limit of wastes stored on the site at any one time is limited to 100 tonnes
- sort, separate, grade, manual feed, cut (using hand-held equipment only), shear, bale and compact
- operate a metal recycling facility in line with the fire prevention plan in schedule 3
The location rules restrict the operation of the facility, so that it is not:
- within 200 metres of a European site, Ramsar site, Site of Special Scientific Interest or Marine Conservation Zone
- within a groundwater source protection zone 1 or 2, or where a source protection zone has not been defined then not within 100 metres of any well, spring or borehole used for the supply of water for human consumption (includes private water supplies)
Small end-of-life vehicle depollution and dismantling facility (less than 750 tonnes) with associated fire prevention plan (SR 2021 No.12) will allow the operator to:
- operate a vehicle storage, depollution and dismantling facility that stores no more than 10 end-of-life vehicles at any one time and accepts less than 750 tonnes of end-of-life vehicles a year
- depollute end-of-life vehicles and sort, separate, grade or cut waste into different components for recovery
- operate a vehicle storage, depollution and dismantling facility in accordance with the fire prevention plan in schedule 3
The location rules restrict the operation of the facility, so that it is not:
- within 200 metres of a European site, Ramsar site, Site of Special Scientific Interest or Marine Conservation Zone
- in a groundwater source protection zone 1 or 2 – or where a source protection zone has not been defined then not within 100 metres of any well, spring or borehole used for the supply of water for human consumption (this includes private water supplies)
- within 10 metres of an unculverted watercourse
Why your views matter
We want your views on our proposed 2 new standard rules permits and their associated fire prevention plans and generic risk assessments. We will review your feedback and change our draft standard rules if appropriate.
What happens next
Thank you for responding to this consultation.
We may make your response publically available (excluding personal information and financial data) on our online tool whilst the consultation is running, unless you have requested that we do not publish your response.
Following the end of the consultation we will produce a consultation response document and this will be published on this consultation’s web page. If you have given us your email address, we will email you to let you know when this has been published.
Thank you
Audiences
- Members of the public
- Elected representatives, including MPs
- Local councils
- Academics
- All water abstractors
- Environment Agency customers
- Metal recycling trade associations and site operators
- Operators
- Trade associations and business
- Other regulators
- Members of the public
- Community groups
- Non-governmental organisations with an interest in environmental issues
- Environment Agency colleagues
Interests
- Waste